Home    •    Company Info    •    International    •    Resources    •    News & Events    •    Contact Us
Home
Contact Us
Contractor's Equipment
Steel Trench Shields
Aluminum Shields
Slide Rail System
Manhole Shields
Shore-Trak System
Inner Shield Liners
Hydraulic Shores
Horizontal Walers
Stone Mizers
Material Separators
Pipe Pullers
Porta-Tanks
Road Plates
SnowBuckets
Municipal Equipment
Build-A-Box
XLAP
HydraShield
Hydraulic Shores
Horizontal Walers
Rescue Shores
Shoring Trailer
Municipal Steel Shields
Porta-Tanks
SnowBuckets
 
Engineering
Tabulated Data
MSDS
OSHA Regulations
Specials!
Training
How To...
International
News & Events
Published Job Stories
Company Information
Catalogs
Videos
Contact Us
Home

 


D.P. Nicoli, Efficiency Production help contractor update
Sacramento State’s sewer system to “Green” status
 

California State University - Sacramento (Sacramento State) is “going green.”  They have several new building projects underway which are incorporating aspects of “green building,” a process to create buildings and supporting infrastructure that minimize the use of resources, reduce harmful effects on the environment, and create healthier environments for people.

 One of the green building projects at Sacramento State includes upgrading the sewer system on campus.  A new 33 thousand gallon holding tank and pump station were recently installed to augment the current system.  Tidelands Construction Company from Brentwood, California, was the general contractor installing the tank and pump station.

 On a busy campus such as Sacramento State, a project such as this was not going to be easy or routine.  The excavation site had very limited access and many surrounding obstacles to contend with, including:

·        A main road for the university and an adjacent parking structure
·       
A drainage ditch and railroad line in close proximity on the opposite side of the excavation from the road
·       
An existing pump station and generator near the excavation site
·       
High volume of both vehicle and pedestrian traffic on the adjacent road

 There was little to no room for equipment access except from the ends of the long, deep and narrow excavation, unless the road was closed.  Shoring the pit was a major challenge as traditional sheet piling or sloping was not an option.

D.P. Nicoli, Efficiency Production Provide Shoring Solution
D.P. Nicoli, Inc. was contacted to help solve the shoring problem. Ryan Jaffe, V.P. of Slide Rail Shoring, worked with Phil Toelkes, Owner of Tidelands Constructions, and J. M. Turner Engineering to come up with a shoring plan that would work for the unique and challenging situation, yet still be affordable and relatively easy for the contractor to install.

 D.P. Nicoli consulted with Mike West, Vice President of Engineering at Efficiency Production, Inc. – the country’s leading manufacturer of trench shielding and shoring equipment.  D.P. Nicoli proposed utilizing Efficiency's Slide Rail System in a six-bay, 4-Sided Multi-Bay Configuration.  Nicoli’s experience with large pits using Efficiency’s slide rail and the patented waler system seemed like a good fit.

 “Efficiency’s Slide Rail really was the perfect solution,” says Hans Vermeulen, Project Engineer with Turner Engineering.  “Everything went according to how it was drawn up.”

  “I’d worked with Nicoli for other shoring needs, but never for the Efficiency Slide Rail,” says Tony Zottola, Project Superintendent for Tidelands Construction. “Installation went really sweet all the way to the bottom without any binding or twisting.  With other slide rail systems I’ve used, I’ve needed to get into the hole and weld the system just to hold it together so it wouldn’t fall apart,” Zottola added.

“Dig and Push” system reduces over-excavation
Efficiency’s Universal Slide Rail is a component shoring system comprised of steel panels (similar to trench shield sidewalls) and vertical steel posts.  The versatile system can be used in a variety of configurations, such as small four-sided pits; large unobstructed working pits as big as 50 x 50 ft. with Efficiency’s ClearSpan System; or in a linear Multi-Bay configuration to install length of pipe over 40 ft.

 Slide Rail is installed simultaneously as the trench or pit is excavated by sliding the panels into integrated rails on the posts–either double or triple rails depending on needed depth–then pushing the panels and posts incrementally down to grade as the pit is dug; a process commonly referred to as a “dig and push” system.

Big clearance for tank made easy with Efficiency Slide Rail
The entire excavation needed to be 16 ft. wide and 89 ft. long.  The tank was 64 ft. long and needed to be placed in a single pick set at 28 ft. deep.

 The biggest challenge was engineering a shoring system that would provide an unobstructed open clearance to the pit of at least 60 ft.  That is where Efficiency’s Slide Rail System provides an advantage over other manufacturer’s slide rail.  Efficiency’s multi-bay configuration utilizes unique parallel beams that incorporate into the vertical posts and pin-in-place standard trench box spreaders as cross-members.  The parallel beams have rollers, and when horizontal walers and sacrificial members are utilized, the entire cross-member apparatus can be easily removed resulting in an unobstructed clearance to the shored excavation!

  “Compared to other systems the Efficiency slide rail has a little more room to play with because of the integrated rails on the posts and the moveable parallel beams sliding along the face of the posts,” Zottola added.  “This was very beneficial due to the limited access that we had.  We could only install from a couple of spots around the pit, but we had no problem handling the system’s components.”

 Slide Rail is unique in that it is installed and removed incrementally, which allows the trench to be properly shored throughout the entire installation or removal process, maximizing the stability of the surrounding ground.  “Clearly, we had no safety issues with the system, it was very safe,” said Zottola.

The system was engineered to incorporate a 60 ft. long W24x162 I-beam welded onto a larger W36x300 I-beam waler, which was then welded to the outside of the vertical posts at the top.  Sacrificial beams were placed at the shoes of the linear posts below grade, to eliminate the potential of deflection when the cross-member assembly was removed.  D.P. Nicoli, Inc. supplied all the slide rail components and had their Senior Slide Rail Specialist, Bruce Ellis, on hand to work with the Tidelands crew.

Tank installation smooth and easy
Tidelands began the excavation by first benching and sloping down about 8 ft.  The slide rail system components included four, 32 ft. vertical corner posts and five sets of 32 ft. linear posts; and 5 in. thick, 14 ft. long, 8 ft. and 4 ft. tall slide rail panels. Tidelands used a Kobelco 400 excavator to install the system.

 Water was encountered at 30 ft.  A 6 in. pump was inserted and the water piped thru a small sediment tank.  A small Bobcat excavator was lowered into the pit to help finish the final grade.

 The base and first section for the pump were set and backfilled at 28 ft. deep.  After the walers were secured to the posts and the sacrificial beams put in place, three of the five Efficiency parallel beam-spreader assemblies were removed for the tank set.  The result was an unobstructed pit that was 60 ft. long and was able to accommodate the 64 ft. long tank.

 A crane was brought in to set the tank.  The tank was also hooked up with a separate strap attached at one end to the excavator, which helped guide the nose of the tank under the last sets of spreaders.  The tank was then sand-bagged in place and backfilled.  Tidelands also used a CAT 375 excavator when removing the slide rail components.

 The entire tank and lift station installation–from first cut to backfill– took about four weeks in October 2006.

 D.P. Nicoli is a one-stop resource for the shoring and piling needs of the heavy construction industry, offering a wide variety of materials and equipment for sale or rent.  They currently serve the Western United States from three facilities in Oregon and Northern California.  Celebrating their 25th Anniversary, DPN has developed lasting relationships with both large and small customers.

 Efficiency Production, Inc., “America’s Trench Box Builder™,” provides the widest selection of standard and custom trench shielding and shoring systems.  Efficiency’s versatile products are designed specifically for safe and cost effective installation of utility systems and infrastructure improvements.  All products are P.E. certified to meet OSHA and MIOSHA standards.

###


Tidelands Construction Company from Brentwood, California, was the general contractor installing a new sewer holding tank and pump station on the Campus of California State University in Sacramento. The sewer upgrade is part of a “green building” initiative.

 The excavation site had very limited access and surrounding obstacles including a main campus road, a drainage ditch, and a railroad line. D.P. Nicoli and Turner Engineering worked with Tidelands to devise a shoring solution utilizing Efficiency Production’s Slide Rail System.

Efficiency’s Slide Rail in a multi-bay configuration utilizes unique parallel beams that incorporate into the vertical posts and pin-in-place standard trench box spreaders as cross-members. The parallel beams have rollers, and when horizontal walers and sacrificial members are utilized, the entire cross-member apparatus can be easily removed resulting in an unobstructed clearance to the shored excavation.

After the I-Beam walers were secured to the posts and the sacrificial beams put in place, three of the five Efficiency parallel beam-spreader assemblies were removed for the tank set. The result was an unobstructed pit that was 60 ft. long and was able to accommodate the 64 ft. long tank.

 

www.epi-shields.com is developed and maintained by Efficiency Production, Inc., 2003

webmaster

 

visitor agreement