|
|
|
The Anchorage Water and Wastewater Utility recently let a $7 million bid to install 4,200 linear feet of hi-capacity 48 in. steel spiral water main pipe, in 40 ft. joint lengths. Taking on the challenge is Pruhs Construction, Inc.. of Anchorage. The new pipeline is part of the larger project, the Anchorage Waterloop project. Contractor Contacts
America’s Trench Box Builder for Assistance Efficiency Production, Inc., headquartered in Michigan, is a leading manufacturer of trench shields and shoring and has a strong reputation for custom engineering trench shielding systems to meet unique shoring challenges. Mike West, Efficiency’s V.P. of Engineering, came up with a plan for a long in-line trench shielding system that met the soil and pipe requirements. Explained West, “We finalized a custom-designed system that combines a 30 ft. and a 24 ft. long trench box into one 54 ft. modular unit. The boxes can quickly and easily be put in and pulled out of the trench as the pipe installation progresses, and it doesn’t require extraordinarily heavy equipment.” Efficiency Production
“Super Arch” Trench Boxes Save the Day “We’ve actually built a couple of these ‘Super-Arch’ boxes for other projects that have needed the extra length for long pipe installs,” explains West. “In each situation, the contractor has been very happy with the trench shields, and they have worked very well.” Darbous agreed, “It worked really well, exactly how we had planned it. It definitely met our expectations. Though it was heavy, our machines were able to handle the two shields without a problem.” Darbous added that he is very happy with the progress his crew is making. The trench boxes were also extremely helpful in the conditions experienced along the pipeline install. “There are two advantages to using a trench box, rather than open cut. The first is that with limited space, you cannot cut back all you want. There were several electrical poles nearby, and open cut would have undermined the poles,” explained Darbous. “Second, it’s very helpful controlling costs associated with bedding and trench backfill by limiting the amount of disturbed soil, because there is less dirt to take out, and less material and backfill to put back. Pea-gravel is expensive around here and hard to come by.” The Anchorage Water Loop project consists of installation of approximately 5,700 feet of 48-inch water main and related appurtenances. The project is part of an alignment change to a segment of the original transmission main, and is necessary to avoid conflicts with existing utilities. When completed, the new transmission main will provide continued capacity to the city-wide water distribution system. The Right Tools for the
Job Pruhs Construction , Inc.. specializes in major civil construction work. Founded by Dana Pruhs 12 years ago, the company has grown from bidding $500,000 contracts to $40 million dollar contracts. Efficiency Production, Inc., “America’s Trench Box Builder™,” provides the widest selection of standard and custom trench shielding and shoring systems. Efficiency’s versatile products are designed specifically for safe and cost effective installation of utility systems and infrastructure improvements. All products are P.E. certified to meet OSHA and MIOSHA standards. # # #
|
| |||||||||