|
How To . . .
The following information is useful for determining the
proper trench shielding for your projects.
How
to Size a Trench Shield
Depth of cut* ____________
Soil conditions*
Type A (25#) ____________
Type B (45#) ____________
Type C (60#) ____________
Hydrostatic ____________
* see depth certification chart
Outside Pipe Diameter___________
(Shield must be a minimum of 12
wider than the pipe.)
Pipe Length ___________
(Shield must be 2 to 4 longer than
the pipe.)
Bucket Width ___________
(Inside shield: 12 less than shield.)
Machine Lift Capacity ___________
(1.5 times shield weight at 20 radius.) |
The following will explain how to determine
the specifications listed above.
How to determine the depth of cut:
g
Slope must start 18 or 1.5
feet below the top of the Shield.
How to determine the width of a trench shield:
g
Trench Shield width determined by O.D. of
the pipe or the O.D. of the excavator bucket.
g
Allow 6 of clearance on each side of
pipe bell.
g
Shield should be a minimum of 12 wider
than the excavator bucket O.D.
How to Determine the
length of a trench shield:
g
Inside length clearance of pipe is
approximately 2 ft. less than the overall length of the shield.
g
Shield must be 2 to 4 longer than the
pipe.
How to Determine the machine lift capacity:
g
1.5 times the shield weight at
20 ft. radius at grade.
Calculating Depth
Ratings
g
PSF ratings and depths are based
on short term exposure with excavation open a period of time equal to 24 hours
or less.
Lateral pressure per foot of depth:
g
Type A Soil = 25 lbs.
g
Type B Soil = 45 lbs.
g
Type C Soil = 60 lbs.
Depth rating using shield capacity (lbs.):
g
1200 / 25 = 48 ft.
g
1200 / 45 = 27 ft.
g
1200 / 60 = 20 ft.
Soil Definitions
g
Apparent
cohesion
g
Cemented
soil
g
Layered
soil
g
Plastic
g
Saturated
soil
g
Submerged
soil
No soil is Type A if:
g
it is
fissured.
g
it is
subject to vibration.
g
it has
been previously disturbed.
g
it is part
of a sloped, layered system which dips into the excavation on a slope of 4
horizontal to 1 vertical [4H:1V] or greater.
g
it is
subject to other factors requiring classification as less stable.
Type B Soil
g
Cohesive
soil with unconfined compressive strength greater than 0.5 tsf but less than 1.5
tsf.
g
Granular
cohesionless soils, e.g., gravel, silt, silt loam, sandy loam.
g
Type A
fissured or subject to vibration.
g
Unstable
dry rock.
g
It is part
of a sloped, layered system which dips into the excavation on a slope less steep
than [4H:1V], but only if the material would otherwise be classified as type
B.
Type C Soil
g
Cohesive
soils with unconfined compressive strength of 0.5 tsf or less.
g
Granular
soils including gravel, sand, and loamy sand.
g
Submerged
soil or soil from which water is freely seeping.
g
Submerged
rock that is not stable.
g
Sloped,
layered system which slopes into an excavation at an angle of 4H:1V or steeper.
Sloping vs. Trench Shields
Items having a high potential for cost over
runs are:
g
Excessive excavation due to
trench sloping.
g
Trucking excavated material from
the job site.
g
Importing specified trench
backfill material.
g
Excessive crew down time due
to waiting for bedding stone or repair of damaged existing utility.
g
Roadway and lawn restoration.
g
Pipe testing and leak repair.
g
Documenting sewer and lead
locations.
Unnecessary excavation due to sloping results
in:
g
Higher trucking costs for
removing excavated material.
g
Higher cost of importing
backfill.
g
Higher street and lawn
restoration.
g
More excavator cycles per cut.
g
Higher crew costs due to
increased time of waiting for excavator to cut sloped trench.
g
Lower pipe production.
g
Possible liquidated damages due
to inefficiency.

The High Cost of
Restoration
Street and lawn restoration costs for projects in cities and subdivisions can be
higher than the cost of laying the pipe. This illustration shows how the proper
use of trench shields eliminates unnecessary excavation thus reducing the damage
to streets, lawns, sidewalks, and existing utilities.

|